| 10.0 MW BIOMASS BASED POWER PROJECT IN DIST. NAGPUR, MAHARASHTRA. |
| i |
General Name of the Company Implementing the Project |
RAKE POWER LIMITED |
| |
Capacity of the project |
10 MW
|
| |
Project Cost |
Rs. 41.40 Crores
|
| |
Shareholding pattern (present) of each SPV |
(95% subsidiary of Shalivahana Projects Ltd)
|
| ii |
Project Background Brief history of project, methodology of award etc. |
The project has been sanctioned by the state government of Maharashtra vide Final Consent letter No.PGN/BPP/009-A/2005-06/1642 dated 16.3.2006.
|
|
Detailed Project Report (DPR) |
DPR has been submitted to MEDA the state nodal agency and the same has been approved.
|
| |
Site accessibility & transportation infrastructure |
The project site is easily accessible.
BT road is available up to project site.
|
| iii |
Power Evacuation Proposed evacuation of power from the Project |
The power will be evacuated 132 KV transmission lines to MSEDCL S/S.
|
| |
Nearest Sub-station of Power grid |
132 KV Sub station at MASAR about 5 KM from project site.
|
| |
Cost of laying Dedicated Transmission Line |
About Rs. 90 lacs
|
| |
Implementation time frame |
Project will be commissioned by end of Dec’07
|
| |
Power wheeling arrangement, if any |
Will be made with MSEDCL
|
| iv |
Power Sale Framework Proposed power sale framework, copy of PPA if already entered into |
PPA has been entered in to with M/s.MSEDCL for 13 years.
|
| |
Tariff at with the power from the Project is proposed to be sold |
Rs. 3.17 for 07-08 and about 4 paise increase every year.
|
| v |
Present status of Project Clearances Techno-Economic Clearance |
Obtained.
|
| |
State Government Clearance |
MEDA final clearance obtained.
|
| |
Pollution Board Clearance |
MPCB consent obtained.
|
| |
Environment & Forest Clearance |
NA
|
| |
Relocation & rehabilitation issues (if any) |
NA
|
| |
Status of Land acquisition |
Already acquired about 25 acres of land in Sy. Nos. 429,432 and 433
|
| |
Likely timeframe for obtaining of each approval |
All clearances like Gram panchayat NOC, Zilla Parishad PHC, land conversion etc obtained.
|
| vi |
Project Implementation Consultants appointed for the Project |
Appointed.
|
| |
Proposed scheme of implementation of the Project |
Civil works completed. Erection of equipment in final stages.
|
| |
Project Development / Implementation Agreement with State Govt. / Govt. agency |
Obtained.
|
| |
Implementation time frame (Project start & end date, scheduled commissioning etc) |
The project is targeted for commissioning by end of Dec’2007.
|
| vii |
Others CDM benefits available to the Project (number of CERs and the sale price of the same) |
Validation protocol will be prepared by DOE by end of December. Registration may be completed by February 2008.
|