10.0 MW BIOMASS BASED POWER PROJECT IN DIST. YAVATMAL, MAHARASHTRA.
i General
Name of the Company Implementing the Project

Shalivahana Projects Ltd.

Capacity of the project

10 MW

Project Cost

Rs. 40.00 Crores
ii Project Background
Brief history of project, methodology of award etc.

The project has been sanctioned by the state government of Maharashtra vide Final Consent letter No.PGN/BPP/035/2005-06/3106 dated 10.5.2006.

Detailed Project Report (DPR)

DPR has been submitted to MEDA the state nodal agency and the same has been approved.

Site accessibility & transportation infrastructure

The project site is easily accessible. BT road is available up to project site.
iii Power Evacuation
Proposed evacuation of power from the Project

The power will be evacuated through 33 KV transmission lines to MSEDCL S/S.

Nearest Sub-station of Power grid

33 KV Sub station at Shindola about 2 KM from project site

Cost of laying Dedicated Transmission Line

About Rs. 15 lacs

Implementation time frame

Project will be commissioned by end of Nov’07

Power wheeling arrangement, if any

Will be made with MSEDCL
iv Power Sale Framework
Proposed power sale framework, copy of PPA if already entered into

PPA has been entered in to with M/s.MSEDCL for 13 years.

Tariff at with the power from the Project is proposed to be sold

Rs. 3.17 for 07-08 and there after about 4 Paise increase every year.
v Present status of Project Clearances
Techno-Economic Clearance


Obtained.

State Government Clearance

MEDA final clearance obtained.

Pollution Board Clearance

MPCB consent obtained.

Environment & Forest Clearance

NA

Relocation & rehabilitation issues (if any)

NA

Status of Land acquisition

Already acquired about 22 acres of land in Sy. Nos. 52,53 and 54.

Likely timeframe for obtaining of each approval

All clearances like Gram Panchayat NOC, Zilla Parishad PHC, land conversion etc obtained.
vi Project Implementation
Consultants appointed for the Project

Appointed.

Proposed scheme of implementation of the Project

Erection completed. Trial runs are in progress.

Project Development / Implementation Agreement with State Govt. / Govt. agency

Obtained.

Implementation time frame (Project start & end date, scheduled commissioning etc)

The project is targeted for commissioning by end of Nov’2007.
vii Others
CDM benefits available to the Project (number of CERs and the sale price of the same)

Validation protocol was filed with UNFCCC by DOE. Registration may be completed by December 2007.