HomeAbout UsCareersTendersFeedbackContact
distilery


 



7.5 MW BIOMASS BASED POWER PROJECT IN DIST. ADILABAD, A.P
i General
Name of the Company Implementing the Project

SHALIVAHANA PROJECTS LIMITED.

Capacity of the project

7.5 MW

Project Cost

Rs. 24.00 Crores
ii Project Background
Brief history of project, methodology of award etc.

The project has been allotted by the state govt. of Andhra Pradesh and commissioned in Dec’2002. The project is operated successfully with out any break for the last 5 years.

Detailed Project Report (DPR)

DPR has been approved by the govt. of AP before commissioning the project.

Site accessibility & transportation infrastructure

The project site is easily accessible. About 1 KM from Mancherial. BT road is available up to project site.
iii Power Evacuation
Proposed evacuation of power from the Project

The power is evacuated through 33 KV transmission lines to state grid.

Nearest Sub-station of Power grid

132/33/11 KV Sub station at MANCHERIAL about 0.5 KM from PH.

Cost of laying Dedicated Transmission Line

About Rs. 6 lacs

Implementation time frame

Project has already been commissioned.

Power wheeling arrangement, if any

NA since the power is supplied to the State Govt. only.
iv Power Sale Framework
Proposed power sale framework, copy of PPA if already entered into

PPA has been entered in to with APTransco. Copy of PPA is enclosed.

Tariff at with the power from the Project is proposed to be sold

Present tariff is Rs. 3.18.
v Present status of Project Clearances
Techno-Economic Clearance


Obtained.

State Government Clearance

Obtained.

Pollution Board Clearance

Obtained.

Environment & Forest Clearance

NA

Relocation & rehabilitation issues (if any)

NA

Status of Land acquisition

Already acquired.

Likely timeframe for obtaining of each approval

All required permissions are in place.
vi Project Implementation
Consultants appointed for the Project

Project has been already commissioned and in operation for the last 5 years.

Proposed scheme of implementation of the Project

-----

Project Development / Implementation Agreement with State Govt. / Govt. agency

-----

Implementation time frame (Project start & end date, scheduled commissioning etc)

------
vii Others
CDM benefits available to the Project (number of CERs and the sale price of the same)

Project got registered with UNFCCC under CDM. CER’s of 1,08,000 got credited on to Jan 2007 and sold @ Euro 9.75 during fin yr 2006-07.

Present status of development activities

PPA was executed with APTRANSCO for 6 MW against installed capacity of 7.5 MW. We got permission from Nodal agency to sell balance 1.5 MW to 3rd party.

@ 2007 shalivahanagroup.com  All Rights Reserved.

power construction eco tourism education distilery