| 7.5 MW BIOMASS BASED POWER PROJECT IN DIST. ADILABAD, A.P |
| i |
General Name of the Company Implementing the Project |
SHALIVAHANA PROJECTS LIMITED. |
| |
Capacity of the project |
7.5 MW
|
| |
Project Cost |
Rs. 24.00 Crores
|
| ii |
Project Background Brief history of project, methodology of award etc. |
The project has been allotted by the state govt. of Andhra Pradesh and commissioned in Dec’2002. The project is operated successfully with out any break for the last 5 years.
|
|
Detailed Project Report (DPR) |
DPR has been approved by the govt. of AP before commissioning the project.
|
| |
Site accessibility & transportation infrastructure |
The project site is easily accessible.
About 1 KM from Mancherial. BT road is available up to project site.
|
| iii |
Power Evacuation Proposed evacuation of power from the Project |
The power is evacuated through 33 KV transmission lines to state grid.
|
| |
Nearest Sub-station of Power grid |
132/33/11 KV Sub station at MANCHERIAL about 0.5 KM from PH.
|
| |
Cost of laying Dedicated Transmission Line |
About Rs. 6 lacs
|
| |
Implementation time frame |
Project has already been commissioned.
|
| |
Power wheeling arrangement, if any |
NA since the power is supplied to the State Govt. only.
|
| iv |
Power Sale Framework Proposed power sale framework, copy of PPA if already entered into |
PPA has been entered in to with APTransco. Copy of PPA is enclosed.
|
| |
Tariff at with the power from the Project is proposed to be sold |
Present tariff is Rs. 3.18.
|
| v |
Present status of Project Clearances Techno-Economic Clearance |
Obtained.
|
| |
State Government Clearance |
Obtained.
|
| |
Pollution Board Clearance |
Obtained.
|
| |
Environment & Forest Clearance |
NA
|
| |
Relocation & rehabilitation issues (if any) |
NA
|
| |
Status of Land acquisition |
Already acquired.
|
| |
Likely timeframe for obtaining of each approval |
All required permissions are in place.
|
| vi |
Project Implementation Consultants appointed for the Project |
Project has been already commissioned and in operation for the last 5 years.
|
| |
Proposed scheme of implementation of the Project |
-----
|
| |
Project Development / Implementation Agreement with State Govt. / Govt. agency |
-----
|
| |
Implementation time frame (Project start & end date, scheduled commissioning etc) |
------
|
| vii |
Others CDM benefits available to the Project (number of CERs and the sale price of the same) |
Project got registered with UNFCCC under CDM. CER’s of 1,08,000 got credited on to Jan 2007 and sold @ Euro 9.75 during fin yr 2006-07.
|
| |
Present status of development activities |
PPA was executed with APTRANSCO for 6 MW against installed capacity of 7.5 MW. We got permission from Nodal agency to sell balance 1.5 MW to 3rd party.
|